Pacific Construction Services, Inc.

Government

Fermilab CUB Tank Replacement  Building 44 Chiller Repairs Repair Stone Copings and Cornice Brick

Fermilab CUB Tank Replacement, Batavia, IL

Building 44 Chiller Repairs, Belleville, IL

Honor Guard Roof Building 386, Belleville, IL

This project consists of the installation of a new 5,000-gallon stainless steel tank for low conductivity water along with new pumps and controls system. The new tank was transported to the facility in three pieces and welded together in the field due to the limited height restrictions in the building. Once the installation of the new tank is complete the existing 3,000-gallon tank will be taken out of service and removed. This project consists of a complete mechanical renovation of the main chiller plant at Scott Air Force Base in Belleville IL. Project activities include the installation of two new chillers and three new cooling towers along with extensive piping and electrical upgrades. Also, chilled water pumps and piping were replaced in six additional buildings connected to the main chiller plant. This project is a complete reroof and installation of a new fall protection system of the Honor Guard Building at Scott Air Force Base in Belleville IL. Project activities include removal of the existing roofing system, installation of a new EPDM roofing system, and installation of a new fall protection system. Also, masonry restoration and repairs throughout the building.

Repair Stone Copings and Cornice Brick Construct B405 MHRRTP James A. Lovell Federal Health Care Facility Buildings 131, 133 & 134.

Repair Stone Copings and Cornice Brick, Belleville, IL

Construct B405 MHRRTP, Tomah, WI

James A. Lovell Federal Health Care Facility Buildings 131, 133 & 134. Chicago, IL

This project consists of masonry restoration to the Scott Club Building at Scott Air Force Base in Belleville IL. Project activities included the repair and replacement of coping stones and cornice brick as well as tuckpointing in order to prevent water infiltration into the building. After all masonry repair work is complete the entire building will be hydroblasted and a sealer applied. Building 405 at the Tomah VA facility is a 30,000 SF, three story building consisting of an architectural precast panels and hollowcore slabs. The awarded contract includes a complete buildout of the third floor patient rooms, as well as a partial buildout of the mechanical and electrical rooms on the first floor. Once completed, the building will connect to building 404 through a newly installed tramway. Upgrade of building perimeter security and Information Resource Management rooms (IRM), this requires extending the Lenel Security System to enable a "Lock-Down" of the subject buildings through the Lenel Access Control System, at multiple locations. The works include the conversion of the doors currently controlled by a standalone GE system in Building 133EF. Installation of electronic locks at noted IRM spaces to control access is also required. Additional electronic door lock features, control system expansion required wiring, programming, testing and upgrade of Lenel software and some door and door hardware replacement shall also be required.

Child Development Center Great Lakes Naval Station Security Forces Operation Facility Child Development Center

Great Lakes Naval Station, Great Lakes, IL

Security Forces Operations Facility,
Scott Air Force Base, IL

Child Development Center, Scott Air Force Base, IL

$12.2 Million $7.2 Million
Design/Build of Building 80H, which is the Center for Explosive Ordinance Disposal and Diving (CEODD) for fitness and swim training/diving programs. Facility wide repairs include abatement of hazardous material, exterior repairs of damaged areas. The building's fire alarm system and electrical system will be replaced. The existing HVAC systems including the pool dehumidification system will be replaced. Gymnasium repairs include the repair and refinishing of walls, blinds, replacement of switches, removal of existing basketball hoops and associated equipment, renovation of gymnasium storage room, and renovation of gymnasium restroom. Pool area repairs include a dehumidification system throughout the pool and locker room areas. Additional pool area repairs include the removal and replacement of existing pool deck with rubberized flooring as well as removal and replacement of existing pool deck floor drains and remaining plumbing pipe work. The pool will be resurfaced while plumbing penetrations will be replaced. Pool area repairs also include replacing the suspended acoustical ceiling tile, light fixtures, and radiators. Pool area to be repainted, existing pool ladders and anchorage elements are to be replaced, and existing electrical receptacles are to be repaired. Design/Build consisting of 34,619 sq. ft. of space. The building includes administrative areas, training and classroom areas, conference rooms, ballistic proof control center, alarm room, long term detention and interview rooms serving both Active and National Guard security operations. Design/Build consisting of 23,594 sq. ft. of space. The building includes playroom and classroom areas for infants thru pre-school children, administrative areas, laundry and kitchen, plus common areas including a break room.

U.S. Army Reserve Marine Corps Reserve Center U.S. Army Reserve Center Security Forces Facility

Marine Corps Reserve Center, Chicago, IL

U.S. Army Reserve Center, Neenah, WI

Rock Island National Cemetery - Veteran Affairs, Rock Island, IL

$1.9 Million $9.1 Million $10.1 million
Renovation of major fire protection upgrades, exterior and interior electrical work, security surveillance with fencing & gate modifications, HVAC/plumbing, asphalt & concrete paving, and site storm drainage. Construction of new 40,065 sq. ft. Army Reserve Center (ARC), a 5,678 sq. ft. Organizational Maintenance Shop (OMS) and a 1,788 sq. ft. Unheated Storage Building (UHS). New Burial Area expansion on 23-acres, includes grave sites in pre-placed crypts, columbaria niches, new committal shelter, public restrooms,and water distribution system.

Atlantic Fleet Drill Hall Building 1425 Building 441 Atlantic Fleet Drill Hall

Building 1425 - Replace Chiller System, Great Lakes Naval Station, IL

Building 441 - Repair Gym Floor, Great Lakes Naval Station, IL

Atlantic Fleet Drill Hall, Great Lakes Naval Station, IL

$276,480 $255,000 $13.4 Million
Replace chiller system for the Combat Training Pool. Remove and replace damaged areas of gym floor. Removed manually operated bleacher bank and replace with eight section integral electrically power bleacher bank. Design, build & maintenance of a 60,000 sq. ft. drill hall facilities including administrative offices, recruit drill hall area, and classrooms; building equipment & furnishings; site utilities; security system, and landscaping.

Building 441 Ray Street Repairs SDDC Facility Building 200H

Ray Street Repairs, Great Lakes Naval Station, IL

SDDC Facility, Scott Air Force Base, IL

Building 200H - Replace Elevator Controls, Great Lakes Naval Station, IL

$223,000 $12.7 Million $2.3 Million
Repaired north end of Ray Street. Replaced existing pavement, curb & gutter, and concrete sidewalk. Removed deteriorated concrete slab under old pavement, repaired inlet/storm utility & soil stabilization. Design/Build 75,000 sq. ft. modular temporary facility including all utility infrastructure, modular building shell & interior finishes, roofing, MEP, classified & unclassified communications, access & intrusion detection systems. Replacement of elevator controls & CAB for West & East Bank elevators of the Naval Hospital. Completed this project 3-months ahead of schedule.

Farragut Bridge Building 2016 Memorial Kiosk Farragut Bridge

Building 2016 - Install HVAC, Great Lakes Naval Station, IL

Memorial Kiosk, Great Lakes Naval Station, IL

Farragut Bridge, Great Lakes Naval Station, IL

$530,000 $577,512 $3.6 Million
.Design and construction of a new HVAC system for 1st floor of Bldg. 2016. New construction of the north and south memorial plaza, including new parking, handicapped ramps, landscaping, plaza paving, large brick pier monument signs and lighting. Demolition of existing steel frame bridge and replaced it with a new structurally sound bridge supported on pile driven shafts.